Case Studies

“Our critical plate supplies were late by nine months. Our fabrication contractors mobilized only 60% of the required workforce. Yet we finished the shipyard in a record 28 months, only four months late against our ambitious goal.”

L&T Shipyard PR Prabhu
Sr. Vice President